Home News [Special project] Commissioning of a boiler house at a reinforced concrete products plant

[Special project] Commissioning of a boiler house at a reinforced concrete products plant

04.03.2021

The boiler house for a reinforced concrete products plant was completed entirely by the FACI-RUS Plant, from design to commissioning. Our task was to manufacture a pellet boiler, install its piping on site and start it up in the shortest possible time (15 working days). Since water from a borehole had to be heated, it was decided to install a heat exchanger.

All tasks were completed ahead of schedule. The boiler house has been put into operation and works without complaints.